|
|
|
|
|
NEW CONSTRUCTION, NOW COMPLETE! |
|
|
On Sunday, November 12, 2000, groundbreaking ceremonies were held for a new Fellowship hall, with a new first floor entry, kitchen and rest rooms. The new downstairs area will include much - needed space for additional rooms for classes, music, and youth. |
|
|
|
Architect's conceptual west elevation of existing church with new fellowship hall addition construction beginning 2001.
|
|
|
|
The first vestiges of things to come appeared Friday, April 6 with the beginnings of excavation by bulldozer. | |
|
Footings were poured 4/27/01 using a concrete pumper truck with a 175' reach. | |
|
The next step was for the forms to be erected and the front foundation walls to be poured. | |
|
The front foundation walls were poured within 5 days of the front footings and within the week the remaining footings were poured, including the elevator shaft footings. | |
|
The new floor was poured on 5/17/01. Now for the beginnings of steel superstructure! | |
|
The steel superstructure and upper floor poured in June and the basic roof structure completed in July. | |
|
During the month of August, the structure was enclosed and many of the interior walls were framed. | |
|
During the month of September, framing inside was competed, much of the electrical, plumbing and HVAC systems rough-in was completed. Additionally the exterior began taking on near - final appearance. | |
| Dedication Service was on January 6, 2002. |