NEW CONSTRUCTION, NOW COMPLETE!

 

On Sunday, November 12, 2000,  groundbreaking ceremonies were held for a new Fellowship hall, with a new first floor entry, kitchen and rest rooms.  The new downstairs area will include much - needed space for additional rooms for classes, music, and youth.  

 

Architect's conceptual west elevation of existing church with new fellowship hall addition construction beginning 2001.

 

            

The first vestiges of things to come appeared Friday, April 6 with the beginnings of excavation by bulldozer.
Footings were poured 4/27/01 using a concrete pumper truck with a 175' reach.
The next step was for the forms to be erected and the front foundation walls to be poured.
The front foundation walls were poured within 5 days of the front footings and within the week the remaining footings were poured, including the elevator shaft footings.
The new floor was poured on 5/17/01.  Now for the beginnings of steel superstructure!
The steel superstructure and upper floor poured in June and the basic roof structure completed in July.
During the month of August, the structure was enclosed and many of the interior walls were framed.
During the month of September, framing inside was competed, much of the electrical, plumbing and HVAC systems rough-in was completed.  Additionally the exterior began taking on near - final appearance.

See the finished product.

  Dedication Service was on  January 6, 2002.